Skip to content
MaximumEnergy Solutions

Industrial battery storage and site power

Battery power for cranes, hoists and constrained sites

Battery storage for construction and industrial projects. Plan around your equipment, charging supply and operating schedule, then get a project-specific proposal.

A white battery enclosure behind red and white barriers on a wet construction site, with cables across the ground and a site worker walking past an unfinished concrete building
Illustrative imageA battery system in a site service area. Equipment and layout vary by project.
Nominal output
193–386kW
Nominal DC energy
215–430kWh
Overload, for up to 10 seconds
585kW
Enquiries from
UK · IE · EU · US · CA

Across the Ampd 200 and Ampd 400. Manufacturer-published figures; full ratings and sources are on the product pages.

Why sites add a battery

Three jobs a battery does well

Not every site needs one. These are the situations where stored energy changes the numbers.

  1. A generator running all day for a small load

    Generators are sized for the biggest demand, then spend most of the day lightly loaded. A battery lets the generator run fewer hours at a sensible load, or lets a smaller one do the job.

    Generator + battery systems
  2. A grid connection smaller than your peaks

    The connection covers the average demand but not a crane lift or a motor start. A battery charges steadily from the connection and supplies the peaks above its limit.

    Limited grid site power
  3. Hours when a generator cannot run

    Night-time, noise limits or air-quality conditions can rule out an engine at set times. Stored energy carries a defined quiet period, charged outside those hours.

    Construction site batteries

Applications

Start from what you need to power

Our current range suits heavy site duties. These are the three we see most.

A white battery enclosure inside temporary fencing beside the base of a tower crane, with a power cable running across wet concrete

Tower cranes and hoists

Short, high lifting peaks with long gaps between them. The question is whether peaks fit inside the overload durations and the day’s energy fits the battery.

A generator and a larger battery enclosure side by side on gravel, with cables in yellow ramps and stacked site cabins behind, on a frosty morning

Construction temporary power

Loads change as the job moves from groundworks to fit-out. Plan around the phases, the charging source and who is responsible for distribution.

A grey supply cabinet beside plywood hoarding on a narrow site access road, with a battery enclosure opposite and a crane and concrete core behind

Constrained grid connections

When the available supply is smaller than the peak demand, a battery can buffer it, provided the connection still covers the energy used over the day.

Illustrative images, not customer projects. Equipment and layout vary by project.

Site offices, welfare cabins and smaller loads

The units in our current range are substantial industrial systems. For smaller loads we assess the requirement first and confirm whether a suitable system can be supplied, rather than assume a fit.

Request an assessment

How it works

Three arrangements, set by the charging source

A battery stores energy; it does not create it. Every arrangement starts with where the energy comes from and when.

Arrangement A

Grid + battery

Charge from an available connection and use the battery to meet short, higher demands or set operating periods. The connection has to supply the site’s energy over the day.

The grid connection charges the battery at a steady rate. The battery supplies the site, covering peaks that are higher than the connection could supply directly.
Arrangement B

Generator + battery

Run the generator when it is useful for supply and charging, and use stored energy during low-load or quiet periods. The generator stays; it runs less.

The generator runs for part of the day to charge the battery and support heavy demand. The battery supplies the site the rest of the time, so the generator is not left running for small loads.
Arrangement C

Battery-only, for a defined duty

Meet a known load for a known time from stored energy, with a verified plan to recharge or exchange the battery before the next duty.

The battery supplies a known load for a known time from stored energy, then recharges from a verified source before the next duty.

Compare battery, diesel and hybrid arrangements

Products

Ampd 200 and Ampd 400

Two mobile battery systems made by Ampd Energy. Nominal output and capacity first, then the short overload ratings that matter for motor starting and lifts.

Full specification comparison

Ampd 200

IEC · Rev 1.3 · 29 April 2026

Nominal output
193kW
214 kVA
Nominal DC energy
215kWh
Usable AC energy is lower
Overload, time-limited
233 kW / 248 kVA for up to 60 seconds
Overload, time-limited
292 kW / 297 kVA for up to 10 seconds
Maximum charging input
205 kW
Supply arrangement
380 to 415 Vac, 3Ph + N + PE
Maximum wet weight
5,500 kg

Ampd 200 specifications and options

Ampd 400

IEC · Rev 1.3 · 29 April 2026

Nominal output
386kW
428 kVA
Nominal DC energy
430kWh
Usable AC energy is lower
Overload, time-limited
466 kW / 496 kVA for up to 60 seconds
Overload, time-limited
585 kW / 595 kVA for up to 10 seconds
Maximum charging input
410 kW
Supply arrangement
380 to 415 Vac, 3Ph + N + PE
Maximum wet weight
9,000 kg

Ampd 400 specifications and options

Source: Ampd 200 IEC brochure, Rev 1.3, dated 29 April 2026; Ampd 400 IEC brochure, Rev 1.3, dated 29 April 2026. Manufacturer-published figures for the IEC variant, not independently tested. Specifications can change, so the current data sheet for your territory is confirmed in a project proposal.

Find your likely power setup

Five quick answers. Choose “Not sure” wherever you need to.

Likely approach

Answer the questions to see a likely arrangement.

You will get a starting point, the reasons for it, and the information an engineer will ask for. Your answers carry into the project brief, so nothing is entered twice.

From brief to site

What happens after you send a brief

  1. Brief

    You describe the site, the equipment and the problem. Unknowns are fine.

  2. Technical review

    A specialist supply partner assesses load, charging supply, schedule, environment and access.

  3. Proposal

    You receive the proposed equipment and configuration, the costs, and who you would contract with.

  4. Fulfilment

    Delivery, commissioning and support are arranged through the supply partner named in the proposal.

Timescales depend on the project and are agreed once the technical scope is understood. We would rather give you a date we can keep than a headline turnaround.

Questions

Before you enquire

More about who we are and how projects run on the about page.

Do you supply the batteries yourselves?

Maximum Energy Solutions is a distributor. We help you specify the requirement and take your project brief to a specialist supply partner, who carries out the technical assessment and supplies the system. Your proposal states the equipment, the costs and the party you would contract with.

Can a battery replace a generator completely?

Sometimes, for a defined duty with a reliable way to recharge. More often on construction sites the battery works with a grid connection or a generator. A battery stores energy; it does not create it, so something still has to supply the energy the site uses over the day.

How do I know what size I need?

You do not need to know before you enquire. A current generator rating or a list of the main equipment is enough to start. Sizing depends on your average load, your peaks and how long they last, and the charging supply available, which is what the technical review establishes.

Will a battery save money on my site?

It depends on fuel use, hire rates, project length and one-off delivery and installation costs. Short projects and small fuel bills can make a battery the more expensive option. Our cost comparison shows the arithmetic with your own figures, including when the answer is no.

Which countries do you cover?

We take enquiries from the UK, Ireland, continental Europe, the United States and Canada. Product variants, approvals and service differ by country, so availability is confirmed for each project rather than promised in advance.

Can I hire rather than buy?

Tell us your preference in the brief, or choose “open to advice”. Which routes are available depends on the project, its location and its duration, and is confirmed in your proposal.

Tell us about the site for a project-specific proposal

A short brief is enough to start. “Not sure” is an acceptable answer to every technical question, and you see a summary of your project before you add any contact details.